Knowledge Hub > Case Studies > Orega Colmore Building Server Room

Orega Colmore
Building Server Room

Client Orega

Project Type – New Installation within server room

Date – February 2020

Orega Colmore Building Server Room ac unit
Orega Colmore Building Condenser

Project Overview

MAC were called in to look at supplying supplementary air conditioning within the server room.

We undertook a site survey along with the building engineers, which lead to a quotation to supply and install a Mitsubishi Electric 10KW wall mounted split system. The pipe run was approx. 40m which had to be ran down the riser to the under-ground carpark area where the condenser would be located.

A new power supply would also need to be installed from the tenant’s distribution board.

Outcome

The system was successfully installed, pressure tested and fully commissioned, work was carried out at weekends to avoid disruption within the office environment.

The power supply was also fully installed and signed off and tested by our electrician.

The engineer installed a tank pump underneath the wall mounted unit to accommodate the volume of water produced in a server room environment.

The condenser wall floor mounted on anti-vibration feet.

Orega Colmore Building Condenser